Project Control Plane DAG Consumption

Synced 2026-10-23 · Updates are made in the source repository.

Project Control Plane DAG Consumption

Purpose

This document defines the minimum platform capability required for platform-template-bootstrap to orchestrate the first project-control-plane build.

Current State Assessment

The platform already has two strong foundations:

  1. a canonical task-graph model
  2. an ExecPlan projection model

Existing evidence:

  • spec/task-graph.schema.yaml
  • docs/planner-execplan-projection.md
  • docs/remaining-work-graph.md
  • docs/codex-orchestrator-execution-loop.md

That means the platform already knows how to:

  • treat graph state as canonical
  • project graph state into governed ExecPlans
  • traverse bounded ready work
  • preserve projection-versus-authority boundaries

Gap For This Project

The missing piece is not a new graph engine.

The missing piece is an explicit way to package a subset of graph nodes into a higher-order grouped execution slice without replacing the canonical graph.

For project-control-plane, that grouped layer is:

  • grouped foundation exec plans
  • grouped implementation packets
  • grouped DAG bundles that reference task-node ids

Required Capability

platform-template-bootstrap must support two linked views:

1. Task-Level DAG

This remains canonical for dependency traversal.

Examples:

  • fnd-001
  • fnd-002
  • fnd-003

2. Grouped DAG Bundle

This is a projection that packages multiple task-level nodes into one governed execution slice.

Examples:

  • foundation bootstrap
  • bronze scan model
  • silver contract model

The grouped bundle must be projection-only. It cannot replace the canonical task graph.

Platform Rule

The platform should treat grouped DAG bundles the same way it treats ExecPlans:

  • as governed projections
  • sourced from canonical graph-backed state
  • lineage-preserving
  • bounded

Minimal Implementation Direction

The first implementation slice should add a grouped execution-bundle contract that:

  • has a stable bundle id
  • references one source DAG id
  • references one source ExecPlan id where applicable
  • carries an ordered list of node ids
  • carries scope and status metadata
  • can expand into task packets

Non-Goals

This slice should not:

  • replace the task graph
  • introduce a second canonical graph
  • redesign the entire orchestrator
  • generalize every future bundle concept up front

Acceptance

The platform is sufficient for project-control-plane when it can:

  1. ingest the task-level DAG
  2. ingest a grouped DAG bundle projection
  3. validate that grouped bundles reference legal node ids
  4. expand a grouped bundle into bounded task packets
  5. preserve lineage from bundle to task packet to execution outputs